Joel Raduma Ramogo & Mary Atieno Ondoro v Integrity Holdings Limited [2021] KEELC 3669 (KLR) | Injunctive Relief | Esheria

Joel Raduma Ramogo & Mary Atieno Ondoro v Integrity Holdings Limited [2021] KEELC 3669 (KLR)

Full Case Text

REPUBLIC OF KENYA

IN THE ENVIRONMENT AND LAND COURT AT THIKA

ELC CASE NO. 173 OF 2019

JOEL RADUMA RAMOGO........................1ST PLAINTIFF/APPLICANT

MARY ATIENO ONDORO........................2ND PLAINTIFF/APPLICANT

VERSUS

INTEGRITY HOLDINGS LIMITED.............DEFENDANT/RESPONDENT

RULING

The matter for determination is the Notice of Motion Application  dated 20th November 2019, by the Plaintiffs/ Applicants seeking for the following orders;

a) That pending the hearing and determination of this suit, this Honorable court be pleased to issue an order of injunction to restrain the Defendant, its servants, workmen, licensees agents or any other person acting on their own behalf or on behalf of the defendant from howsoever continuing any works of building and construction, rebuilding, excavating, renovating, plastering, masonry works, concrete works, finish works, roofing, screeding, installation of windows, doors and or fixtures and or continuing any forms of construction works whatsoever on title Number DAGORETTI/ KINOO/5214, and spreading debris or interfering with plaintiffs and their tenant peaceful entitlement, possession and enjoyment of Title Number DAGORETTI/KINOO/6181.

b) That the OCS - Kinoo Police Station does assist in enforcement of any oders issued herein.

c) That the cost of this application be borne by the Defendant.

The Application is premised on the grounds that the Plaintiffs/Applicants are the registered owners of the suit property having acquired it in2016, and developed the same. That the Defendant/ Respondent is the registered and beneficial owner of L.R Dagoretti/Kinoo/5214, which is adjacent to the Plaintiffs/ Applicants property which it acquired in 2018.  That the Defendant/ Respondent is continuing to construct a block of residential flats on  its said land  without any properly approved  designs  and in a manner that has caused complete blockage of light  to the Plaintiffs/ Applicants part of the premises. Further that the Defendant’s/ Respondent’s  construction has also caused  water leak to the Plaintiffs/Applicants premises thereby causing severe cracks and the water is causing flooding into the Plaintiffs/ Applicants units. That the Defendants/ Applicants shoody construction is  posing grave danger  to the Plaintiffs/ Applicants  premises.

That the Plaintiffs/ Applicants  had intensively borrowed  to finance the construction and as such the lack of tenants  due to the Defendants/Respondents actions is causing  great prejudice and they  stand to lose their investments  of  over Kshs. 80,000,000/=and other  properties  charged to secure financing of the  instant development. That it is in the interest of Justice that the Application be allowed.

In her Supporting Affidavit, Mary Atieno Ondoro, averred that she has authority to swear the Affidavit on behalf of the other plaintiff. That they are the registered owners of title no. DAGORETTI/KINOO/6181,and they constructed a total of 32 residential flats, comprising of one and two bedroom and that construction was funded by various loans and sale of various properties which they co-own situated in Western Kenya. That she had severally talked to the Defendant/Respondent purported DirectorMR CHARLES KURIAto stop the constructions and consider changing the designs  of the construction but he had totally ignored the request.  That on 15th NOVEMBER 201, she reported the matter to Kikuyu Sub County offices in charge of planning and development who only called for a site meeting on8th NOVEMBER 2019,but failed to appear at all. Due to Defendants/Respondents actions, she said that at least six tenants had moved out and no one is interested in taking up houses there causing them to lose income amounting to Kshs 140,000/=monthly.

The Application is  opposed vide a Replying Affidavit sworn on  16th December 2019, by Charles Kuriathe Defendant’s/ Respondent’s  Director. It was his contention that the orders sought by the Plaintiffs/ Applicants are misplaced, unwarranted, prohibitive and ought not to be granted. That most projects are funded through loans and the Plaintiffs/ Applicants  is not a unique case and their action to charge their matrimonial homes are not in any way connected to the Defendant’s/ Respondent’s  deeds.

That the Defendant/Respondent  is the beneficial owner of L.R No. Dagoretti/Kinoo/5214, next to the Plaintiffs/ Applicants. It was his contention that  any blockage  is a direct consequences of the  Plaintiffs/ Applicants  having failed to take cognizance of future developments.  That  he started his construction after securing approvals from the County Government of Kiambu. Further that  the boundary wall which the Plaintiffs/ Applicants  blame for blocking light was constructed as per the building approvals. That Plaintiffs/ Applicants  have no capacity to ascertain what a poorly supervised and totally shoddy construction is. Further  that the Plaintiffs/ Applicants  lighting problems emanated from changing their approved designs of balconies and windows and at no particular time has his construction been stopped by Sub County authorities.  That tenants  paying monthly rent  and who do not hold  a tenancy agreement  with the Plaintiffs/ Applicants  for fixed duration cannot  be considered as income lost. That the Court  should not be inclined  to grant any orders as his construction is fully up and  only minor finishing works are ongoing.

The Plaintiffs/ Applicants filed a Supplementary Affidavit sworn by   Mary Atieno  Ondoro  on  14th January 2020, and averred that it is improbable  that any County Authority  could have approved the Defendant’s/ Respondents  construction or building plans  without an Environmental Impact Assessment  report, NEMA licenses  and approvals, structural and mechanical plans by  qualified engineers. That the Architectural  plans attached in the Replying Affidavit  only shows  that five floors were to be built,  but on the ground , the construction has gone up to seven floors. That the issues of water leaking into their premises and repainting premises have been discussed severally with Mr. Kuria,  and he agreed to take corrective measures.

The Application was canvassed by way of written submissions which the Court has carefully read and considered .The Court having carefully considered and evaluated the available evidence and    the exhibits thereto, the written submissions, cited authorities and the relevant provisions of law finds that the issue for determination is whether the Applicants  are entitled to the injunctive orders sought.

In determining whether or not the Plaintiffs/ Applicants are entitled to injunctive orders, the Court  is guided by the principles as set out n the case of  Giella …Vs… Cassman Brown  (1973) EA 358 and as was reiterated in the case of  Nguruman Limited ….Vs… Jan Bonde Nielsen & 2 others CA No.77 of 2012 (2014)eKLR where the Court of Appeal held  that;

“in an interlocutory injunction application the applicant has to satisfy the triple requirements to a, establishes his case only at a prima facie level, b, demonstrates irreparable injury if a temporary injunction is not granted and c, ally any doubts as to b, by showing that the balance of convenience is in his favour.

These are the three pillars on which rests the foundation of any order of injunction interlocutory or permanent.  it is established that all the above three conditions and states are to be applied as separate distinct and logical hurdles which the applicant is expected to surmount sequentially.”

Before the Court  makes a determination on whether or not, it should grant the injunctive orders sought, it  notes that the Defendant/ Respondent in its submission dated 10th November 2020, submitted that  the Orders sought by the Plaintiffs/ Applicants cannot be enforceable  as  the Application has been overtaken by events  and therefore ought to be dismissed for lack of practical  purposes as the building has been built to completion. The Court notes that the Plaintiffs/ Applicants sought for injunctive orders to restrain the  Defendant/Respondent from continuing with the Construction, rebuilding amongst  other works. That the Plaintiffs/ Applicants produced in evidence photographs of  an unfinished  building.

It is trite that he who alleges must prove.   While  the Court is cognizant of  the fact that the orders were sought on 20th November 2019, and this Ruling is set to be delivered on 15th  April 2021, and being that there were no interlocutory orders, the building might have been  completed, there is no evidence of such completion. Further the Court also notes that the injunction was against the peaceful  occupation of their land by the Plaintiffs/ Applicants and thus  it cannot find that the Application has been  overtaken by events without any evidence to support the same.

On whether the Plaintiffs/ Applicants have established a prima facie case;-A prima-facie case was described in the Mrao Ltd… Vs… First American Bank of Kenya Ltd & 2 Others (2003) KLR 125, to mean;-

“In civil cases, it is a case which on the material presented to the Court or a tribunal properly directing itself will conclude that there exist a right which has apparently been infringed by the opposite party as to call for an explanation or rebuttal from the latter.”

It is not in doubt that the Plaintiffs/ Applicants are the registered owners of L.R Dagoretti/Kinoo/6181, in which they have built  residential houses. The Plaintiffs/ Applicants have averred that the Defendant/ Respondent who is the registered owner of L.R Dagoretti/Kinoo/ 5214, commenced construction and interfered with  the peaceful occupation of their tenants  as the same has  blocked part of their  premises and denied several units  any form of lights. That the shady constructions has leaned  dangerously on their premises and caused cracks  and caused flooding which interfered with their property.

The Defendant/ Respondent acknowledged  that there were minimal damages  that might have occurred  to the Plaintiffs/ Applicants property  at the initial  stages and he employed mitigating factors.

The Court has  also seen the text messages that suggests that indeed the Defendant/Respondent’s construction did interfere with the Plaintiffs/ Applicants  building   and the photographs evidence of the same. Every person has a right under the Constitution to peaceful and  quiet enjoyment of their rights and any actions that interferes with the same is therefore  an infringement  of these rights.

The Defendants/ Respondents having interfered with the Plaintiffs/ Applicants quiet and peaceful use and possession of their property, would only mean that the Plaintiffs/ Applicants have established a prima facie case with a probability of success as there exists a right that has allegedly been infringed.

On whether the Plaintiffs/ Applicants will suffer irreparable loss;-  ‘Irreparable loss’ was described in the case of Paul Gitonga Wanjau…Vs…Gathuthi Tea Factory Co. Ltd & 2 Others, Nyeri HCC No.28 of 2015, as simply injury or harm that cannot be compensated by damages and would be continuous.In the Case of Niaz Mohammed Janmohammed …Vs… Commissioner  for Lands & 4 Others (1996) eKLR, the Court held that:-

“It is no answer to the prayer sought, that the Applicant may be compensated in damages.  No amount of money can compensate the infringement of such right or atone for transgression against the law, if this turns out to have been the case.  These considerations alone would entitle the Applicant to the grant of the orders sought.”

Apart from interference with the Plaintiffs/ Applicants  quiet  and peaceful possession of the suit property by causing slippage and leaking  flood, the Plaintiffs/ Applicants have also accused the Defendant/ Respondent of building without necessary approvals and building more floors than what was approved in its Architectural designs. The Court has seen the said Architectural designs produced by the Defendant/ Respondent in evidence and notes that indeed what was approved was five floors and  what the   Defendant/ Respondent’s building as per what  produced as photographic evidence is 7 floors. Further apart from the Architectural drawing no other approval has been produced in evidence. These allegations have not been rebutted by the Defendant/ Respondent and in as much as  the Court recognizes that  it ought not to make definitive findings at this stage, the said allegations have not been refuted and the Court finds no reason to find otherwise.

If indeed the Defendant/ Respondent is building without the necessary approvals and further if they are going beyond the approved  floors, it therefore follows that  the Plaintiffs/ Applicants who are adjacent to them may suffer irreparable loss that may not be compensated by way of damages as the same  may be the cause  of the damages  caused to their building. The Court therefore finds and holds that if any further constructions  would continue assuming any other, then the risk of the Plaintiffs/ Applicants suffering irreparable loss is high and the Defendant/ Respondent ought to be injuncted.

On the third limb ofif the Court is in doubt then it ought to determine  the matter  on the balance of convenience,the Court is not in doubt at all. Even so the  balance of convenience always tilts in favour of maintaining the status quo. For avoidance of doubt the status quo in this case will be  the condition the  Defendant’s/Respondent’s building is in at the time of the Ruling

Having now carefully considered the Notice of Motion Applicationdated20th November 2019,brought by the Plaintiffs/Applicants herein, the Court finds it merited and the same is allowed entirely in terms of prayers no. 3 and 5of the said Application.

It is so ordered.

DATED, SIGNED AND DELIVERED AT THIKA THIS 15TH DAY OF APRIL 2021.

L. GACHERU

JUDGE

15/4/2021

Court Assistant -  Phyllis

ORDER

In view of the declaration of measures restricting court operations due to theCOVID-19 Pandemic, and in light of the directions issued by His Lordship, the Chief Justice on 15th March 2020, this Rulinghas been delivered to the parties online with their consents. They have waived compliance with Order 21 rule 1 of theCivil Procedure Rules which requires that all judgments and rulings be pronounced in open Court.

With Consent of and virtual appearance via video conference – Microsoft Teams Platform

No appearance for the Plaintiffs/ Applicants

Mr. Kimani for the Defendant/Respondent

L. GACHERU

JUDGE

15/4/2021