Kudheiha Workers Union v Gerald Mwangi [2015] KEELRC 1199 (KLR)
Full Case Text
REPUBLIC OF KENYA
EMPLOYMENT AND LABOUR RELATIONS COURT
AT NAIROBI
CAUSE NO. 1254 OF 2010
KUDHEIHA WORKERS UNION………………………CLAIMANT
VERSUS
GERALD MWANGI…………………RESPONDENT/APPLICANT
CORRECTION OF JUDGMENT
Under Rule 33 Industrial Court (Procedure) Rules 2010
As part of the decision of Kosgey J. (as he then was) on 15th December 2011 housing of 2,500 x 24 months was granted. This sum is Kshs. 60,000/- and not 112,211 as appears on the Judgment. I correct the sum to read 60,000/- in place of 112,211. There is no order as to costs for correction of errata as the mistake was that of the Court.
Orders accordingly.
Dated and delivered at Nairobi this 9th day of February 2015
Nzioki wa Makau
JUDGE