Okello v Sukari Industries Co Limited [2023] KEHC 21488 (KLR)
Full Case Text
Okello v Sukari Industries Co Limited (Civil Appeal 22 of 2019) [2023] KEHC 21488 (KLR) (31 July 2023) (Judgment)
Neutral citation: [2023] KEHC 21488 (KLR)
Republic of Kenya
In the High Court at Homa Bay
Civil Appeal 22 of 2019
KW Kiarie, J
July 31, 2023
Between
Kapis Otieno Okello
Appellant
and
Sukari Industries Co Limited
Respondent
(Being an Appeal from the judgment in Ndhiwa Senior Resident Magistrate’s SRMCC No. 178 of 2017 by Hon. S.K Arome –Senior Resident Magistrat)
Judgment
1. Kapis Otieno Omollo, the appellant herein was the plaintiff in Ndhiwa Senior Resident Magistrate’s SRMCC No 178 of 2017. He had sued the respondent for compensation for three crops on allegations of breach of contract. The learned trial magistrate delivered judgment dated February 6, 2019 in which the claim was dismissed.
2. The appellant was aggrieved by the said judgment and filed this appeal. He was represented by the firm of Kerario Marwa & Company Advocates. He raised grounds of appeal as follows:a.That the learned trial magistrate erred in law and fact when he failed to find and hold that the duty to harvest contracted sugarcane was statutory therefore needing no notice written or verbal.b.That the learned trial magistrate erred in law and fact when he dismissed the appellant’s case on the ground that he should have invoked the arbitration clause and yet the jurisdiction of the court had been invoked by the filing of the defence.c.The learned magistrate erred in law and in fact when he determined the case against the weight of evidence.d.The learned trial magistrate erred in law and fact when he disregarded statutory provisions of the Sugar Act, which by then was the law applicable to sugarcane contracts.e.The learned magistrate erred in law and fact when he was not clear in his judgment whether he had dismissed the plaintiff’s case or not.f.The learned magistrate erred when he applied a narrow interpretation to the contract.
3. The respondent was represented by the firm of Ogejo, Olendo & Company, Advocates who contended that the appellant did not prove his case in the trial court.
4. This court is the first appellate court. I am aware of my duty to evaluate the entire evidence on record bearing in mind that I had no advantage of seeing the witnesses testify and watch their demeanor. I will be guided by the pronouncements in the case of Selle vs Associated Motor Boat Co Ltd[1965] EA 123, where it was held that the first appellate court has to reconsider and evaluate the evidence that was tendered before the trial court, assess it and make its own conclusions in the matter.
5. The learned trial magistrate had three main issues to address his mind to. These were whether there was a valid contract between the parties, whether failure to enforce the arbitration clause was fatal to the appellant’s case and whether there was breach of contract.
6. Upon perusal of the record, I agree with the finding of the learned trial magistrate that there was a valid contract between the parties.
7. The Cane Farming and Supply Contract at clause 6 provided for arbitration in case of a dispute or disagreement between the parties. This ought to have been raised at the earliest opportunity before the commencement of the trial before the learned trial magistrate. The parties did not do so. The parties therefore submitted themselves to the jurisdiction of the trial court, and it would appear they mutually agreed to disregard their arbitration clause. The finding by the trial magistrate on this issue was therefore erroneous.
8. In his testimony, the appellant testified that he did not write to the respondent. He however said he visited the office and made a verbal report. Clause 3 of their agreement states:"Should either party commit a breach of this agreement and fail to remedy such breach within thirty (30) days after receipt of a notice in writing to that effect from the other party serving such a notice, the party not in breach may, by further notice in writing shall be at liberty to terminate this agreement from the date of completion of delivery of cane from the next ensuing harvest."
9. This clause does not envisages a situation where either party faced with a breach of contract will sit and fold hands and await to file a suit. The appellant did not testify that he gave the contemplated notice in writing and that he took the necessary steps to terminate the contract and to ameliorate the loss. In the case of William Kazungu Karisa v Cosmus Angore Chanzera [2006] eKLR where the court (Ouko J as he then was) stated:"The basic rule of the law of contract is that the parties must perform their respective obligation in accordance with the terms of the contract executed by them. For instance, the contract must be performed at the time and place agreed upon. Where no specific period for the performance of the contract is agreed then it must be completed within a reasonable time, which in turn will depend on the circumstances of the particular situation. However, when a specific dated is mentioned, then time becomes of the essence and completion must be within that date as it becomes a condition which goes to the root of the contract."
10. The upshot of the foregoing analysis of the evidence is that the appeal lacks merit and the same is dismissed with costs.
DELIVERED AND SIGNED AT HOMA BAY THIS 31STDAY OF JULY, 2023KIARIE WAWERU KIARIEJUDGE