PEWIN SUPPLIES LIMITED v PERMANENT SECRETARY, MINISTRY OF PUBLIC WORKS [2009] KEHC 2239 (KLR) | Public Procurement | Esheria

PEWIN SUPPLIES LIMITED v PERMANENT SECRETARY, MINISTRY OF PUBLIC WORKS [2009] KEHC 2239 (KLR)

Full Case Text

REPUBLIC OF KENYA

IN THE HIGH COURT OF KENYA

AT NAIROBI (NAIROBI LAW COURTS)

Miscellaneous Application 367 of 2009

PEWIN SUPPLIES LIMITED………………………………….. APPLICANT

VERSUS

THE PERMANENT SECRETARY,

MINISTRY OF PUBLIC WORKS………..………………… RESPONDENT

RULING

By a Chamber Summons dated 17th June 2009 the ex parte Applicant Pewin Supplies Ltd. Seek the leave of this court to commence Judicial Review proceedings against the Respondent, Ministry of Public Works.  It seeks leave to apply for an order of certiorari to remove into the High Court and quash the decision, order, or directive of the Ministerial Tender Committee Ref No. MPWA/A 164. 17 Vol X (133) and dated 6th June 2008 purporting to have extended in particular the contract for the supply of “Fire Fighting Equipment” and AFFF Foam Compound, safety and emergency Equipment from 30th June 2008 to 30th December 2009.  Leave to apply for an order of prohibition of the Permanent Secretary Ministry of Public Works Prohibiting him from implementing the directives dated 6th June 2008 that purported to extend the contract in issue from 30th June 2008 to 30th December 2009, leave to apply for an order of mandamus directed at the Respondent to advertise for the supply of fire fighting equipment and AFFF Foam compound safety and emergency equipment for the Period 2009-2010.  Lastly, and that the grant of leave do operate as stay of the decision of the Ministerial Tender Committee to extend the contract until the determination of his application.  The application is supported by a statement of facts dated 16th June 2009 and the verifying affidavit of Peter Kirigua the Managing Director of the Applicant.

When Mr. Kamunde, Counsel for the Applicant approached the court for leave, this court directed that the chamber summons be served and be heard interparties.  Mr. Waudo from the State Law Office appeared for the Respondent Law Office and opposed the application on points of law.

Briefly, the facts of this case are that the Respondent advertised a tender for fire fighting equipment and the Applicant was one of the bidders.  On 28th September 2007, the officer in charge, supplies, informed the Applicant that the Ministerial Tender Committee had awarded the tender to the successful bidder (PMK 2).  The Applicant sought to know why its bid was not successful under letter of 2nd October 2007.  They were informed that their tender was disqualified at technical evaluation (PMK 4).  The Applicant was dissatisfied with the decision of the Committee and appealed to the Public Procurement Administrative Review Board vide appeal No. 56/2007 (PMK 5).  However, the Applicant withdrew the appeal upon advise of the Director of Procurement Ministry of Public Works who intimated that the tender would only last upto 30th June 2008 after which the Applicant could apply for tender and he therefore withdrew the appeal (TMK 6).  On 20th June 2008 and 18th July 2005 the Applicant wrote to Respondent complaining that the subject tender was being unlawfully considered for extension to 30th December 2009 (PMK 7 & 8) and on 9th August 2005 the Ministerial Tender Committee confirmed that they had approved and extended the tender to 30th December 2009 and were seeking advice from Public Procurement   Authority (PPOA) on how to proceed (PMK 9).  That on 10th September 2008, the PPOA wrote to the Respondent advising them to abide by the law and allow for competitive bidding.  However, on 17th June 2009 the Applicant received a letter dated 29th May 2009 from the Respondent confirming that the contract for supply of fire fighting equipment was extended to 30th December 2009 vide letter of 6th June 2008 (PMK 11 & 12).  That is the impugned decision.

In reply Mr. Waudo submitted that order of certiorari cannot issue as the application has been made outside the 6 months period allowed under Order 53 Rule 2 Civil Procedure Rules.  That the directive has already taken effect and an order of stay cannot issue.  That since a contract is already in existence it cannot be set aside by way of Judicial Review.  He urged this court to dismiss the application.

At this stage all that the applicant needs to demonstrate to this court is that they have an arguable case with good chances of success.  The Applicant has explained how the said contract has been entered into, it did not comply with the provisions of the Public Procurement and Disposal Act, 2005 whose object is to achieve efficiency, promote competition and ensure that competitors are treated fairly, increase transparency etc (section 2 of the Act).  The Respondent acted contrary to the intent and spirit of the Act and to the advice given by the Public Procurement Oversight Authority that they comply with the Act.  The issue is whether the extension of the contract by the Respondents is ultra vires the Public Procurement and Disposal Act, whether there was fairness in the award of the tender in accordance with principles envisaged in the Act and whether the Respondent considered irrelevant matters in the extension of the contract.  This court is satisfied that an arguable case is disclosed in light of the above stated issue and leave is granted in terms of prayer 1, 2 and 3 of the Chamber Summons.

Can stay be granted?  It seems the contract was granted in 2008 (PMK 8).  Its already one year since the award.  The reasons given for extension is that the contractor had excess materials right over.  Only 5 months are left of its performance and for that reason the court will decline to grant an order of stay at this stage as it may serve to cause confusion and the beneficiaries of the equipment may suffer unnecessarily.  I direct that the Notice of Motion be filed and served within 14 days.

Once Notice of Motion is served the same be listed for mention for purposes of taking directions.

Costs will abide the Notice of Motion.

Dated and delivered this  17th  day of July 2009.

R.P.V. WENDOH

JUDGE

Present

Mr. Waweru holding brief for

Mr. Kamunde   -     Applicant

Mr. Wendoh    -     Respondent

Muturi         -     Court clerk