IN THE SUPREME COURT OF SEYCHELLES RESORT DEVELOPMENT LIMITED Applicant/Defendant (Herein rep by its Managing Director Mr. Serge Gladky) VS. ALLIED BUILDERS (SEYCHELLES) LIMITED Respondent/Plaintiff (Herein rep by its Managing Director Mr. Pravin Darad) Mr. Ally for the Applicant/Defendant Mr. C. Lucas for the Respondent/Plaintiff – Absent Gaswaga, J ORDER Civil Side No. 295 of 2006 This Court has considered the application filed by the Applicants and the affidavit of one Irakli Gharibashvili as well as the submissions of Mr. Frank Ally.    The Court finds the application to be meritorious and accordingly vacates the order of interim injunction that was issued on the 12th day of April, 2007. I so order. JUDGE Dated this 3rd day of May, 2007. D. GASWAGA