Ultra Electic Limited v Triad Architects Limited, Mizphah Contractor Agency & Metrocom Consultants Limited [2021] KEHC 5248 (KLR)
Full Case Text
REPUBLIC OF KENYA
IN THE HIGH COURT OF KENYA AT MERU
CIVIL SUIT NO. E016 OF 2021
ULTRA ELECTIC LIMITED..................................................................PLAINTIFF
VERSUS
TRIAD ARCHITECTS LIMITED ................................................1ST DEFENDANT
MIZPHAH CONTRACTOR AGENCY.....................................2ND DEFENDANT
METROCOM CONSULTANTS LIMITED................................3RD DEFENDANT
RULING
1. I have considered the submissions by parties and I consider that it is important to balance the competing interests of the parties herein. We need to protect the substratum of the dispute and that of the 4th defendant, that the project proceeds to obviate the incidental costs occasioned by stoppage.
2. I note that the plaintiff says that it has spent and outlaid itself in sum of Kshs. 500,000/= which may be lost if injunctive orders in place are not extended.
3. Doing the best I can, I take the view that the disclosed injury, damage is capable of compensation in monetary terms to the extent of the exposure.
4. On that understanding, I do discern no loss beyond the sums spent so far, and maybe incidental injury capable of qualification on monetary terms.
5. Consequently, I do discharge the orders but on terms that the defendants present, 1st, 2nd and 4th, shall deposit into court a sum of Kshs. 700,000 within 48 hours from now.
6. The discharge takes effect upon deposit and in the event that the deposit is not effect the injunctive orders shall stand reinstated from the date of default.
PATRICK J.O OTIENO
JUDGE
01/07/2021